Thai Nguyen: Connecting transport infrastructure brings the economy to the finish line

KIM DUNG - VU PHUONG 02/11/2026, 04:27

Thai Nguyen is accelerating expressway, bridge, and regional connecting road projects, creating development space for industry, logistics, and foreign direct investment attraction. Resolving site clearance and labor bottleneck issues will decide how quickly these projects achieve optimal efficiency.

Thai Nguyen Province currently features an expanded development space, extending from southern industrial hubs to the northern mountainous regions. As the province sets a target for double-digit growth, transportation infrastructure plays a crucial role in connecting markets, widening development space, and attracting investment.

gd.jpg

On the afternoon of October 24, 2026, Mr. Pham Quang Anh, Director of the Thai Nguyen Department of Construction (3rd from right), inspects the actual site preparation for starting several projects in the province. This supports a series of large-scale project groundbreakings scheduled for October 29-30, 2026, celebrating the 195th anniversary of the establishment of Thai Nguyen Province. Photo: Provided by the Department of Construction.

Key connecting axes expanding the economic space

According to the Thai Nguyen Department of Construction, in the third quarter of 2026, the local construction sector grew by 14.16%, contributing 0.84 percentage points to the province's GRDP growth. Civil engineering construction activity rose by 28.99%, while transport and warehousing increased by 14.02%. These results highlight the essential contribution of infrastructure to production and goods circulation.

A prominent project is the complete construction investment project for the CT.07 Expressway (Hanoi - Thai Nguyen - Cho Moi section), which broke ground on June 30, 2026, under the Public-Private Partnership (PPP) model. The route stretches approximately 99 km with a total investment of over 21.228 trillion VND. The Hanoi - Thai Nguyen section will be widened to 6 lanes, while the Thai Nguyen - Cho Moi section will be completed with 4 lanes.

By early October 2026, investors focused on surveying, designing, and preparing construction fronts at priority locations. Localities are simultaneously speeding up site clearance and the relocation of technical infrastructure to facilitate execution. Once completed, CT.07 is expected to enhance transport capacity between the Capital Region and the province's industrial and mountainous areas.

Further along the corridor, the Cho Moi - Bac Kan Expressway—stretching about 28.8 km with an investment of 5.750 trillion VND—had handed over approximately 99% of its site clearance by mid-October 2026. Contractors are accelerating construction, striving for completion in 2027. Together with the Bac Kan - Cao Bang section under investment preparation, these projects aim to form a seamless connection corridor to the border region.

Along the East-West direction, the regional connecting road between Bac Ninh, Thai Nguyen, and Phu Tho—stretching over 42.5 km with a total budget exceeding 4.2 trillion VND—has opened to technical traffic and operational usage, expected to boost connections among industrial and logistics hubs.

Alongside new construction, maintenance of the existing network is prioritized. Leaders of the Thai Nguyen Department of Construction noted that the department manages over 60 km of expressways, nearly 539 km of national highways, and about 1,000 km of provincial roads. It has implemented 23 road repair projects and one bridge inspection project. Maintaining the quality of operational routes, connecting main roads to branch roads, and ensuring traffic safety are just as essential as launching new projects.

The new network is expected to help businesses transport goods more proactively, reduce costs, and expand market access, provided that routes operate safely and integrate synchronously with yards and logistics infrastructure.

1792993863842_1558699623375521074_377184921982290095_9f8a9da2fdfa40144b82b1010dce4324.jpg

The intersection between the Bac Ninh - Thai Nguyen - Phu Tho regional connecting road and the CT07 section passing through Yen Binh interchange, Van Xuan ward. Photo: Vu Phuong.

Unblocking bottlenecks to reach the "finish line"

In the central area, the new Gia Bay Bridge project is one of the key structures receiving prioritized guidance regarding progress. The project aims to improve connectivity across the two banks of the Cau River and ensure flood drainage. As of late September 2026, progress achieved about 37.11% of the contract value; the bridge section aims for technical traffic opening in December 2026, while other items are scheduled for completion in Q1 2027. From October 20 to December 31, 2026, traffic routing is being organized around the Bac Kan Street – Bac Son Street intersection to serve construction.

Mr. Truong Van Trinh, Project Manager of the new Gia Bay Bridge construction project (under Truong Son Construction Corporation, Corps 12), stated that as a Grade I engineering work, the project requires high-speed progress with many items executing in parallel. According to contractor representatives, 100% of mobilized households have received compensation payments and dismantled structures. However, several spots at both bridgeheads still face site clearance issues. The unit is also experiencing pressure due to a shortage of skilled labor, requesting local authority support to resolve site clearance and connect skilled workforce supply.

Mr Trịnh

Mr. Truong Van Trinh, Project Manager of the new Gia Bay Bridge project under Truong Son Construction Corporation, Corps 12, answers an interview with Business Forum Magazine reporters. Photo: Vu Phuong.

Along the same Cau River, the Quang Vinh 1 Bridge, Quang Vinh 2 Bridge, and connecting road network project has a total investment of around 1.528 trillion VND, executing across 2025–2027. To date, work on Quang Vinh 1 Bridge reached 66.5% and Quang Vinh 2 Bridge reached 47.4%, but connecting road No. 1 has only reached about 5%. The main bottleneck remains site clearance and resettlement. The province aims to open technical traffic for both bridges by April 30, 2027.

Based on actual site operations, Mr. Do Van Hong, Vice General Director of Hong Ha Construction and Equipment Investment JSC, shared that several households have not finished resettlement, leaving site availability fragmented. Simultaneous implementation across multiple projects has also caused a shortage of skilled workers. Enterprises recommend accelerating compensation, land handover, and establishing appropriate labor recruitment mechanisms, which directly determine construction rhythm and quality.

Beyond bridge works, the Right Cau River Dike project from Cao Ngan Bridge to Thac Huong Dam carries a dual purpose: flood control and prevention for the provincial center, and forming a transport route combined with riverside urban landscaping. The project has a total investment of over 7.626 trillion VND, with a combined dike and road length of about 16.46 km; two out of four construction packages are underway, though site clearance remains slow.

Mr. Nguyen Tho Phu, Director of the Project Management Board under Lung Lo Construction Corporation (Package No. 2), stated that construction broke ground on July 6, 2026. The contractor regularly coordinates with the investor and local authorities to address difficulties, gain public consensus, and add equipment and manpower in eligible locations. The unit is determined to fulfill its commitment, striving to complete and hand over the project in December 2027. Construction requires the contractor to ensure progress, quality, and structural safety simultaneously.

de.jpg

Mr. Nguyen Tho Phu, Director of the Project Management Board under Lung Lo Construction Corporation (left), presents the layout map of the Right Cau River Dike project section from Cao Ngan Bridge to Thac Huong Dam. Photo: Vu Phuong.

From a operational business perspective, Mr. Nguyen Manh Ha, Chairman of the Thai Nguyen Transport Association and Chairman of the Board of Directors at Ha Lan Trade and Tourism JSC, commended the transport infrastructure developments in recent years. New routes provide more transit options and support trade. However, according to Mr. Ha, many businesses still encounter difficulties regarding parking yards and accompanying logistics infrastructure. The business community hopes recommendations made following dialogues are categorized, assigned clear responsibilities, and resolved promptly, rather than remaining just acknowledged issues.

Construction sites continue to face challenges concerning site clearance, manpower, and materials. The Department of Construction stated it is coordinating to review and unblock issues for 42 delayed and pending projects while enhancing project quality management and ensuring safe traffic. Resolving these phases synchronously will help these projects deliver full economic value early.

For Thai Nguyen, reaching the "finish line" means not only completing bridges and roads on schedule, but also turning these projects into drivers of economic growth.

Author: KIM DUNG - VU PHUONG