Unlocking stalled property projects: A path forward
While recent progress has been encouraging, resolving long-delayed real estate projects requires a synchronized strategy to untangle legal hurdles.
The Grand Manhattan project in Ho Chi Minh City is accelerating its progress after legal obstacles were removed. Photo: Nam Phong
A new legal framework has established a relatively cohesive foundation for resolving difficulties facing real estate developments. However, applying current policies to rectify lingering issues in projects initiated under previous regulations is rarely straightforward.
Legal bottlenecks on the ground
Lawyer Pham Thanh Tuan, a real estate legal expert, said, "Drawing from legal advisory practice, these obstacles generally would fall into three core categories: residential land use conditions for commercial housing developments, operational hurdles encountered during execution, and legacy build-transfer (BT) contracts."
First, Article 127 of the 2024 Land Law imposes stringent criteria regarding residential land when developing commercial housing projects via land use right acquisition agreements or existing land use rights. Consequently, many developers possessing land banks aligned with local master plans still face roadblocks for failing to meet specific land classification criteria.
To address this, the National Assembly issued Resolution No. 171/2024/QH15, followed by the Government’s Decree No. 75/2025/NĐ-CP, piloting commercial housing development through land use rights agreements or existing holdings.
Under the pilot scope, Hanoi encompasses 298 land parcels spanning roughly 1,530 hectares, while Ho Chi Minh City accounts for 361 parcels covering approximately 2,285 hectares. This policy unlocks fresh investment opportunities for sites that previously fell short of residential land stipulations.
The second group of challenges centres around investor selection, land allocation, land-use conversion, land valuation, and administrative procedures.
Nationwide, 4,619 projects are currently facing friction, representing a combined land footprint of roughly 203,660 hectares and total investment capital of VND 3,929.511 trillion. It is important to note that not all of these cases involve regulatory violations.
To clear this backlog, the National Assembly enacted Resolutions No. 170/2024/QH15, No. 265/2025/QH15, and No. 29/2026/QH16, progressively expanding the scope of application for specialized mechanisms.
Results across several localities reflect positive momentum: Hai Phong has cleared 239 out of 249 projects; Hue has unblocked 161 of 171; and Tuyen Quang stands at 51 of 56.
Nevertheless, resolving a single issue does not automatically mean all bureaucratic boxes are ticked. Many projects must simultaneously satisfy land, urban planning, construction, and environmental mandates, while existing regulations fail to cover every emerging scenario comprehensively.
The final category involves legacy BT contracts, where challenges typically stem from contract clauses, the valuation of payment land funds, adjustments to total investment capital, and regulatory shifts over the project lifecycle.
Government Resolution No. 16/2026/NQ-CP provides additional legal backing to resolve legacy issues in this category. Even so, complex cases involving multi-layered problems require tailored case-by-case evaluation.
Four pillars for action
To accelerate the resolution of prolonged projects, Lawyer Pham Thanh Tuan said policymakers and local authorities should focus on four key action areas:
First, differentiating the nature of legal bottlenecks. Some issues stem strictly from procedural missteps during execution, demanding a proportional and context-driven review. Regulators should draw a clear line between administrative oversights and self-serving wrongdoing, ensuring accountability adheres strictly to the law, while leveraging previously issued special-mechanism policies can help reinforce the legal basis for swift resolution.
Second, empowering local authorities. In reality, a single project may simultaneously battle land, investor-selection, planning, architectural, and construction hurdles, far beyond the scope of current catch-all regulations. Provincial People's Committees should be granted targeted, autonomous authority to review multi-faceted cases, provided they respect master plans, prevent State budget losses, and safeguard the lawful rights and interests of the State and all stakeholders.
Third, streamlining legacy BT frameworks. Execution of legacy BT models frequently triggers disputes over contractual terms, payment methods, and mutual obligations. Because many of these deadlocks arise from compounding factors, authorities should broaden evaluation scopes to address shared responsibility transparently, pinpointing core causes and degrees of involvement while upholding the prudent management and utilization of public assets.
Fourth, decoupling personal accountability from project unblocking. Enforcing accountability for involved parties must adhere to statutory frameworks without paralyzing ongoing remediation efforts. Where appropriate, authorities should allow accountability proceedings and project unblocking to move forward in parallel rather than mandating a strict sequential timeline. This dual-track approach upholds legal penalties against wrongdoing while preventing administrative stagnation and returning dormant land resources to productive economic use.
Author: NGOC ANH